Completion of Block B Factory for Carlisle Fluid Technology

This month saw Practical Completion of Block B Factory for Carlisle Fluid Technology (UK) Ltd in Poole. 

Existing services were stripped out of their existing 2,530m2 warehouse and new heating, ventilation, lighting power, coms, compressed air, water and gas were designed for a factory fit-out with more specific mechanical ventilation with heat recovery and VRV air condition to serve a two storey office space built inside the factory.

Worldwise did a load assessment for gas, water and electrical demands in the fit out area.  An upgrade of gas and electrical supplies  resulted for the whole site, with new services extended to Factory B.  A new 630A switchpanel board, 400A busbar trunking distribution, lighting, emergency lighting, high level busbar trunking for small and motive power was designed and specified by Worldwise with existing , fire alarm, CCTV and comms cabling systems extended.  New , gas-fired unit heaters, air source heat pumps for offices and dehumidification to two product preparation areas were detailed along with a compressed air backbone distribution was a designed as a co-ordinated package for fast installation on site.

More News

  • Work Experience

    We continue to offer 14 and 15 year olds a week’s taster session to learn about the exciting industry that we work in. The week allows the students to try ...
  • Quality Assurance

    Worldwise have just completed a top to toe update of their quality assurance ISO 9001 : 2015 manual and processes. The update makes our documentation more customer focussed and more ...
Worldwise © 2026. All Rights Reserved | Privacy Policy | Cookies Policy | Website Design Dorset - Good Design Works