Wimborne Hospital, Outpatients & X-Ray

Location:Wimborne, Dorset

Client: The League of Friends, Dorset Healthcare NHS Trust

Architect: Q P Architecture

Contractor: TSL Projects

Services Value:£360,000

Project Value:£1,400,000

Commenced:April 1999

Completion:September 2000

An Outpatient and Day Surgery extension to Wimborne Hospital comprising reception and waiting areas, consulting rooms, Treatment Room, Recovery, day Theatre, and ancillary spaces. Provision of a new X-Ray suite, audiology & ophthalmology suites also undertaken.

Worldwise undertook the design, specification and construction management of all M&E services including theatre ventilation and lighting, “non-clinical feeling” lighting in circulation areas, replacement 300 kVA standby generator, mains power and switchgear upgrades for site.